公告标题:Abandoned Soil Transportation Service Inquiry
公告内容:
深水港码头项目位于巴基斯坦卡拉奇港Keamari防波堤东侧,为**深水集装箱码头。码头共4个泊位及一个接岸延伸段,每个泊位长375m,延伸段长161.65m,全长1661.65m。码头采用连续锚碇板桩结构形式,前排板桩墙为Ф2.5m带锁扣钢护筒的连续钢筋砼钻孔灌注桩。
The deep-water port terminal project is located on the east side of the Keamari breakwater in Karachi Port, Pakistan, and is a new deep-water container terminal. The dock has a total of 4 berths and a connecting extension. Each berth is 375m long, the extended section is 161.65m long, and the total length is 1661.****. The dock adopts the form of continuous anchor plate pile structure, and the front row of plate pile wall is a continuous rebar drilling and injection pile with 2.5m locking steel cylinder.
The deep-water port terminal project is located on the east side of the Keamari breakwater in Karachi Port, Pakistan, and is a new deep-water container terminal. The dock has a total of 4 berths and a connecting extension. Each berth is 375m long, the extended section is 161.65m long, and the total length is 1661.****. The dock adopts the form of continuous anchor plate pile structure, and the front row of plate pile wall is a continuous rebar drilling and injection pile with 2.5m locking steel cylinder.
主要工作内容包括: 649根Φ2.5m胸墙钻孔桩、577根Φ1.2m后轨梁钻孔桩、622根Φ1.6m锚碇钻孔桩施工,以及胸墙、轨道梁、锚梁现浇,锚杆安装,码头后方回填及附属设施安装等。
The main work contents include: 649 Φ2.5m chest wall drilling piles, 577 Φ1.2m rear rail beam drilling piles, 622 Φ1.6m anchor drilling piles construction, as well as chest walls, track beams, anchor beams in-place, anchor rod installation, dock rear backfilling and ancillary facilities installation, etc.主要工程量为:回填砂石料120万方,混凝土20万方,钢板2.5万吨,钢拉杆0.55万吨及附属结构。
The main project volume is: 1.2 million cubic metres of backfilling sand and stone, 200,000 cubic metres of concrete, 25,000 tons of steel plate, 55,000 tons of steel tie rods and ancillary structures.本次拟计划对堆场处不满足回填要求的9.8万m3弃土进行弃运运输服务招标,由项目现场堆场弃运至业主指定弃土场,需于15个工作日内全部完成。
This time, it is planned to bid for abandoned transportation services for 98,000 m3 of abandoned soil that does not meet the backfill requirements in the storage yard. The project site storage yard shall be transported to the abandoned soil site designated by the owner, which shall be completed within 15 working days. 附件列表
物资信息
1 | 公路货物运输服务 | 公路货物运输服务 | 98000.****0000 | 项 |